Füredi út combined heat and power plant, Budapest

Expansion of Főtáv's Füredi út hot water network system with three new gas engine units.

Expansion of Főtáv's Füredi út hot water network system with three new gas engine units. Construction, commissioning and handover of three gas engine generator sets and their auxiliary systems; design and construction.

Client: Sinergy Kft.

About the facility

Main parameters of the combined heat and power plant:

  • Electrical output: 18.18 MW
  • Thermal output: 17.1 MW

Main equipment:

Gas engines: three units

Supplier: Wärtsilä

Type: 18 V34SG

  • Electrical output: 6.06 MW
  • Thermal output: 5.7 MW
  • Electrical efficiency: 43.9%
  • Thermal efficiency: 34.6%

Electrical system (medium and low voltage):

Supplier: ABB